Challenge – Safely and efficiently decommission the defunct tails line. Visually inspect and perform UT testing on old piping. Pre-spool bypass piping prior to shutdown to minimise risk of schedule slippages. Tie into existing tails pipeline during a plant shutdown and expedite works to shutdown schedule.

Solution – PARC provided a team of Piping Fitters, a Supervisor and specialised tooling, to carry out the works on site at a moments notice. Our experience team systematically decommissioned the defunct tails line, then reinstated it on the bypass and completed the tie-in’s.

Results – The scope was successfully completed on time and without incident.