Mulla Mulla Camp

Challenge – PARC was engaged to accelerate the project closeout of BHP’s Southflank camp upgrade and expansion in Mulla Mulla. This included all ITP’s, MDR, Punch Listing, stakeholder walkdowns and custodial transfers

Solution – To execute this project close-out, PARC supplied mechanical and electrical resources which also helped to manage and complete close out requirements and support the commissioning and hand-over activities.  

Results – The project was completed safely and there were no incidents with the punch-listing, closeout and handover. This allowed for early demobilisation of the client’s key management resources which then meant they could transition to another project while PARC drove project completion.

Project
Southflank Project
Client
Decmil Australia Pty. Ltd.
Location
Newman, Western Australia